Urgently collect non-stop tolls on highways

According to VTV.vn – Expressways across the country are in the final stages of putting non-stop toll collection services into use.

Before the milestone set by the Government to complete the system electronic toll collection On the expressway routes by the end of July, recently, Vietnam Expressway Corporation (VEC) has selected a contractor to lease the service and committed to ensuring the right progress.

Thus, expressways across the country are in the final stages of putting non-stop toll collection services into use, contributing to ensuring transparency and efficiency in toll collection operations.

After bidding, VEC has selected a contractor to lease non-stop toll collection services on all four expressways: Cau Gie – Ninh Binh, Ho Chi Minh City – Long Thanh – Dau Giay, Noi Bai – Lao Cai and Da Nang – Quang Ngai. The expected time for non-stop toll collection is 5 years.

Ho Chi Minh City – Long Thanh – Dau Giay Expressway. (Photo: PLO)

Faced with the pressure of an installation time of just over a month, the service provider affirmed that it would mobilize all its resources in terms of equipment and human resources.

“We will focus on the best personnel to directly manage and implement the project and resolve any arising issues. Secondly, regarding equipment, we have also diversified our supply sources and are ready to accept air transport to meet the schedule,” affirmed Mr. Nguyen The Minh, Vice Chairman of the Board of Directors of Tasco Joint Stock Company.

The winning bidder for the service is the one with the lowest bid. Meanwhile, the implementation time is very urgent. Having resolved the problems that have lasted for many years, this is the time that requires VEC to take responsibility with the contractor to ensure the progress and quality of the non-stop automatic toll collection system.

“VEC has established a steering committee and a working group to implement all four expressways to meet the requirements from now until July 30, especially the two gateway routes to two major cities: Cau Gie – Ninh Binh and Ho Chi Minh City – Long Thanh – Dau Giay,” said Mr. Nguyen Van Nhi, Deputy General Director of Vietnam Expressway Corporation.

There is only more than a month left to complete the huge amount of work, so both the investor, VEC, and the contractor leasing the non-stop toll collection service will have to set a daily schedule, because people and businesses are waiting to use this modern and civilized toll collection method on key highways across the country.